Projects
/
Construction and Installation work
Construction and installation work of the treatment plant expansioin Khanhongor soum, Umnugovi aimag.
Customer:
Umnugovi aimag, Governor's Office
Location:
Dalanzadgad sum, Umnugovi aimag
Implmented date:
2024
Project create
Constructed by E.Temuujin, E.Enkh-Orgil, B.Baasansuren
Project details
Within this work a new 6,000 m3 dual biopond, a 665.6 m protective fence, and a 626 m flood protection channel were constructed at the central treatment plant in Khanhongor soum, Umnugovi aimag. Additionally, eight inspection wells and barrier structures for the sewage line underwent significant repairs.